Update - 19 November 2026

We are pleased to provide an update on the moveable boom project. Specialist contractors will be on site from Thursday 26th to Saturday 28th November, with Monday 30th November reserved as a contingency day if required, to undertake planned rectification works within the 50m pool. 

The works will include: 

  • Installation of additional support components to address bowing within the structure. 

  • Enhancement of specific boom components. 

  • Surface improvements to the boom walkway areas. 

The boom remains stable in its current position and available for public access. The upcoming works are designed to address structural issues and improve its operation. However, further works, testing and commissioning activities are still required before the boom can be repositioned and brought into full operational use. 

To facilitate the works: 

  • The 50m pool will be closed from 8:00am Thursday 26th November until 4:00pm on Friday 27th November. 

  • Half of the 50m pool will remain available after 5:00pm on Thursday evening and prior to 8:00am on Friday morning. 

  • Half of the 50m pool will reopen following this stage on the Friday evening and all day Saturday while remaining works are completed. 

  • Where possible, lap swimming lanes will be available in the dive pool. 

  • No works are scheduled for Sunday 29th November. 

Thank you for your patience and ongoing support as we continue progressing this project. 

 

Update - 30 October 2026

We wanted to provide an update regarding the boom in our 50m pool.

Defects were identified that currently prevent the boom from being safely repositioned. As a result, the boom is not currently in use while a rectification plan is being developed.

The manufacturer, in collaboration with the installation company and our team are in the final stages of developing a rectification plan to address the issues. All rectification works associated with these defects will be undertaken at the contractor's cost.

While progress is being made, we do not yet have a confirmed timeframe for the completion of these works.

Although we don't have all the details at this stage, we wanted to keep our customers informed of the updates we do have. We understand the importance of the boom to many of our users and appreciate your patience while we work towards a resolution.

We want to assure our users that the current 50m pool configuration remains fully compliant for use. The 50m pool was independently surveyed and certified on 6 August, and a current certificate is in place.

The issue relates solely to the operation of the boom and its ability to be safely repositioned, not to the compliance or accuracy of the existing lane configurations.

We will provide a further update as soon as more information becomes available.

Thank you for your understanding and continued support.